Service Provider: BAC Secretariat, End-users, Messengers
Schedule: 8:00 a.m. to 5:00 p.m., Monday to Friday
Clients: University Personnel and Students/End-Users
Fee: None
Processing Time: Fifteen (15) minutes BAC Secretariat Internal Processes; four (4) days waiting time at the End-Users’ responsibility
STEP | ACTIONS TO BE TAKEN | DURATION OF ACTIVITY | STAFF IN-CHARGE | REQUIREMENTS/ FORMS | |
CLIENT | SERVICE PROVIDER | ||||
1 | Submits letter request for change in mode of procurement with justification | Receives the letter request with appropriate attachments | 5 minutes | Willbert D. Hosme | Letter request, PPMP, APP, other attachments (if applicable) |
2 | Informs the BAC regarding the request for referendum of end-user | 2 minutes Waiting time: 2 hours |
Gelina A. Zerrudo Jasmin Mary D. Dalena Mercy Gladys S. Cuenca | Letter request, Project Procurement Management Plan (PPMP), Annual Procurement Plan (APP), other attachments i.e. Line Item Budget, Memorandum of Agreement |
|
3 | Informs the end-user regarding the decision of the BAC | 2 minutes Waiting time: 2 hours |
Gelina A. Zerrudo Jasmin Mary D. Dalena Mercy Gladys S. Cuenca |
||
4 | Signs the APP | 2 minutes | Liza G. Custodio, BAC Secretariat Chair | Project Procurement Management Plan (PPMP), Annual Procurement Plan (APP), other |
|
attachments i.e. Line Item Budget, Memorandum of Agreement |
|||||
5 | Waits for the letter with attachments to be included in the upcoming meeting of the respective BAC, if the request is disapproved | Attaches the list of members of BAC with their respective offices and a note for the end-user to scan the PPMP approved by the BAC, and APP approved by the BAC Chair, Chief of Accounting Office, Vice Chancellor for Administration and Chancellor. The scanned documents shall be forwarded to the respective email addresses of the recording secretaries per BAC, if the request is approved |
2 minutes Waiting time for end-user: 1 day |
Gelina A. Zerrudo Jasmin Mary D. Dalena Mercy Gladys S. Cuenca |
Project Procurement Management Plan (PPMP), Annual Procurement Plan (APP), other attachments i.e. Line Item Budget, Memorandum of Agreement |
6 | Proceeds to the BAC Secretariat Office and collects the documents | Gives the documents and instructs the procedure to the end-user, if the request is approved | 5 minutes | Gelina A. Zerrudo Jasmin Mary D. Dalena Mercy Gladys S. Cuenca | List of members of the respective BAC, letter request, PPMP, APP, other attachments (if applicable) |
7 | Proceeds to the offices of the members of the respective BAC and have them sign the PPMP and APP, if the request is approved | 4 hours | End-user representative | List of members of the respective BAC, letter request, PPMP, APP, other attachments (if applicable) |
|
8 | Proceeds to Accounting Office for the Chief of Accounting Office to sign and approve the APP | 4 hours | End-user representative | Approved letter request, PPMP, APP, other attachments (if applicable) |
|
9 | Sign and approves the APP | 15 minutes Waiting time upon receipt of PPMP and APP: 7 calendar days |
Chief of Accounting Office | Approved letter request, PPMP, APP, other attachments (if applicable) | |
10 | Receives the PPMP and APP approved by the Chief of Accounting Office. Forwards the PPMP and APP to the Office of the Vice Chancellor for Administration for approval |
1 day | End-user representative/ Messenger In-Charge | Approved letter request, PPMP, APP, other attachments (if applicable) | |
11 | Sign and approves the APP | 15 minutes Waiting time upon receipt of PPMP and APP: 7 calendar days |
Vice Chancellor for Administration | Approved letter request, PPMP, APP, other attachments (if applicable) | |
12 | Receives the PPMP and APP approved by the Vice Chancellor for Administration Forwards the PPMP and APP to the Office of the Chancellor for approval |
1 day | End-user representative/ Messenger In-Charge | Approved letter request, PPMP, APP, other attachments (if applicable) | |
13 | Sign and approves the APP | 15 minutes Waiting time upon receipt of PPMP and APP: 7 calendar days |
Chancellor | Approved letter request, PPMP, APP, other attachments (if applicable) | |
14 | Scans the document upon approval of Vice Chancellor for Administration, and sends the scanned copy to the respective email addresses of the recording secretaries per BAC, if the request is approved |
1 day | End-user representative | Approved letter request, PPMP, APP, other attachments (if applicable) | |
End of transaction |